1.
A project manager wants to give some guidelines to the project team as to how risk events should be described. Which of the following items would not be appropriate in describing a risk event?

Login/Register to access massive collection of FREE questions and answers.
Login/Register

PMP Certification
Quiz Index
1500 questions in 150 tests. Each test contains 10 questions.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150

Idiom of the Day

pay (someone) a back-handed compliment
to give someone a false compliment that is really an insult
The woman paid her colleague a back-handed compliment when she told her what a good job she was doing.

Word of the Day

  • Smartphone Photography Tips and Tricks
  • 101 Fitness Tips
  • Myth about Acne
  • Most Valuable Sports Teams in the World
  • Spookiest Abandoned Places
  • Benefits of Chives

  • Swach Bharat Abhiyan

    Swachh Bharat Mission Challenges

    Swachh Bharat Mission looks an ambitious project where the focus is towards building toilets.To make it a mass movement PM Modi has involved many celebrities Salman Khan and Priyanka Chopra as a brand ambassadors for the cause.The government has also contacted yoga guru Baba Ramdev, Art of Living guru Sri Sri Ravi Shankar, the Ramakrishna Mission and the Kanchi Kamakoti Peeth and government is still in the process of pursuing the Catholic Bishops Conference of India and Muslim clerics to become the part of the campaign.


    Chourishi Systems